Overhead crane is Hengjia in workshops, warehouses and empty field for material lifting material lifting equipment. Because of its ends located in the tall concrete pillars or metal bracket, shaped like a bridge. Overhead crane overhead bridge along the laying of tracks on both sides longitudinally running, you can take advantage of the space under the bridge lifting material from ground equipment obstacles. It is the most widely used, the largest number of a lifting machinery.
bridge gantry crane
2013年8月13日星期二
Electric hoist gantry crane load test content and procedures
No load test conditions are normal only after allowing for load test. Load test of static and dynamic two kinds, the first for the static load test, and then the dynamic load test.1, the load test test content.(1) Metal construction gantry crane at the bolted connections and welding quality, mainly primary end beam quality of the connection.(2) machinery and equipment, metal structures and spreader strength and rigidity as well as the strength of the crane rails.(3) brake action should be flexible and reliable work.(4) No noise reducer.(5) good lubricity lubrication parts, the bearing temperature rise does not exceed specified.(6)
The mechanism parts should be smooth, no vibration phenomenon, if any
defects, deficiencies should be repaired and then tested.2, static load test, electric hoist lifting rated load.Running
back and forth the entire length of the bridge after several electric
hoist will be open to the bridge at one end, in the amount column to
find the zero line (ie, the actual height of the beam at this time).Measured
stiffness: the electric hoist bridge open to the middle with a eot crane
hook lifting rated load, leaving the ground 100 ~ 200mm, suspended for
10 minutes, this time measuring bridge girders or lower deflection, A5
grade crane girder deflection under should not exceed L/700.Rated
load test after passing for 25% of the rated load test, overload test
method and rated load test the same eligibility conditions that no
permanent deformation after the test, trial can be connected for three
times. The results of a third subject.3, dynamic load test.(1)
Static load test conditions are normal only after allowing for dynamic
load test, dynamic load test as the date of acceptance of the conditions
are not.(2)
dynamic load test is a constant load in excess of 10% case of repeated
lifting and falling commissioning and operation of institutions in this
load of perishable commissioning and for carts, electric hoist running
terminal switch test.4, the electrical component testing regulations and inspection items:(1) gantry hoist crane agencies repeatedly for continuous operation time does not exceed 15 minutes. Therefore, the test agencies operate alternately. Only when the body is completely stopped before allowing reverse.(2) Check the limit, safety devices, interlocks action is correct and reliable.(3)
failure of the electrical equipment operation, should be eliminated,
not motors and electrical equipment exceeds a predetermined standard
temperature, the movable contact may not have burning conditions, the
device should not abnormal sound and vibration phenomena.